Subiaco WWTP - Perth, WA
Main Contractor: Guidera O’Connor
We were engaged by GOC to work on the upgrade of Water Corp’s Water Treatment Plant in Subiaco. We completed the detailed earthworks, formwork, reo and the pour and installation of underground services.
Formwork and steel fixing
Concrete supply and install of complex circular tank with Launder channel
Bulk Earthworks including managing contaminated soils
Installation of underground conduits and cables
Detailed earthworks
Shenton Park Pump Test Facility - Perth, WA
Main Contractor: Valmec
Valmec engaged CATS to construct a waterproof tank including form, reo and pour at Shenton Park Pump Test Facility.
Formwork and steel fixing
Concrete supply and install of construct rectangular waterproof tank and cover slab
Labour and plant hire
Bold Park Reservoir - Perth, WA
Main Contractor: Valmec
Repeat client Valmec engaged us to complete pipe encasements, slabs, retaining walls and stairs. This included form, reo and pour at Bold Park Reservoir upgrade.
Formwork and steel fixing
Concrete supply and install of encasement of pipes ~ 200m long around 900mm and 600mm diameter pipes at 30% angle uphill
Stairs - FRP
Base Slabs - FRP
Retaining walls – FRP
Bridgetown WWTP – Bridgetown, WA
Main Contractor: Guidera O’Connor
GOC engaged CATS to complete the detailed earthworks, form, reo and pour at Water Corp upgraded Water Treatment Plant in Bridgetown. The project was completed ahead of schedule and on budget.
Formwork and steel fixing
Concrete supply and install
Completed all detailed earthworks
Installation of underground conduits and cables
Plant and equipment supply
Labour and plant hire
Denmark Water Treatment Plant – Denmark, WA
Main Contractor: Guidera O’Connor
We were engaged by GOC to complete the detailed earthworks and placement of 215m3 of concrete at their new Water Treatment Plant in Denmark. We worked closely with the team at GOC to deliver the project within budget and ahead of schedule.
Formwork and concrete supply and install
Completed all detailed earthworks
Steel fixing (reo supply and install)
Rottnest Water Treatment Plant - Rottnest, WA
Main Contractor: Guidera O’Connor
GOC engaged CATS to complete the extension of two walls for water tanks on the incredible Rottnest Island.
Tank wall extensions
Formworking, steel fixing and concrete placement
Labour and plant hire